Capabilities and testing

Customer Witness Testing for Switchgear

Customer witness testing gives project representatives an opportunity to observe agreed inspection and test activities for new switchgear or new retrofit components before shipment. As the manufacturer, we can review a proposed witness plan with the project team and clarify what is available for the quoted configuration. Witness testing is not automatically included: scope, schedule, procedures, documentation and any associated charges must be confirmed in the quotation or other project agreement. We serve Texas from the United States and ship nationwide; the applicable test arrangements are established for each project.

UL 891 switchboardsMADE IN USAFAST lead times
NEW EQUIPMENT. PROJECT FOCUSED.SERVING TEXAS
Electrical switchgear lineup in an equipment room

NEW SWITCHGEAR FOR YOUR PROJECT

MANUFACTURING / EQUIPMENT / TEXAS

Define the witness scope before quotation

Start by identifying exactly which new equipment or new retrofit components are in scope, and what the customer intends to observe. A request might cover a defined inspection, selected electrical or mechanical checks, or review of specified records. The project team should distinguish witness activities from routine manufacturer inspections, tests required by the purchase specification, and any third-party inspection. Those are different obligations and should be stated separately.

For a useful scope review, provide the equipment description, approved drawings or specification, applicable standards, requested test evidence, witness organization and preferred timing. Identify who may approve procedure revisions and who may accept or reject observed results. We will review the request against the configuration and project requirements; inclusion, feasibility, documentation, schedule and cost must be confirmed rather than assumed.

Agree witness points and hold points

A witness point identifies an activity the customer may observe, while a hold point requires a defined release before work proceeds past that stage. The project documents should name each point, the activity involved, the notice required, and the party responsible for disposition. Clarify whether the manufacturer may proceed if a witness does not attend after notice, or whether written authorization is required. Resolve these rules before manufacturing milestones make rescheduling difficult.

Connect each point to the relevant drawing, specification clause, procedure or inspection record. For example, a visual review may depend on an approved layout, while a functional check may rely on a specified control sequence. Avoid broad wording such as “witness all testing” without defining boundaries. A precise schedule helps the customer send the right representative and lets the manufacturer prepare relevant equipment, records and personnel.

Build an agenda around the project

The agenda should state the equipment or component under review, planned activities, expected duration, participants, location, access requirements and document versions. It should also identify prerequisites, such as completion of the agreed assembly stage, approved drawings, test procedure review and availability of required project information. If multiple assemblies or components are included, define the sequence and how each item will be identified in the records.

Confirm the proposed date with the manufacturer before travel is booked or attendance is committed. A witness event depends on project readiness, resource coordination and the agreed scope; a requested date is not a confirmed date until accepted. Specify whether attendance is in person or another arrangement is acceptable, who handles scheduling changes, and how the parties will communicate a delay, incomplete prerequisite or revised agenda.

Review procedures, acceptance criteria and limitations

Before the event, align on the procedure for each witnessed activity, including the equipment configuration, test instruments or records to be used, sequence, acceptance criteria and method for recording results. The procedure should make clear what constitutes a pass, a failure, an incomplete activity or a result requiring engineering review. If the customer specification and proposed procedure differ, resolve the discrepancy in writing before the witness session rather than relying on an informal interpretation onsite.

The applicable activities depend on the equipment and project requirements. Agree whether the witness will observe visual or workmanship inspections, mechanical operation checks, control functions, or other specified procedures; do not assume every possible test is included. Define any excluded work and whether a requested addition requires technical review, procedure revision, schedule adjustment or a change to the commercial scope. Applicable standards and any product listing must be verified for the specific configuration.

Set safety and access expectations

A witness plan must address site or facility rules, permitted areas, required personal protective equipment, attendance limits, photography or recording restrictions, and the person authorized to provide orientation. State these expectations in advance so visitors can prepare and the event can proceed without disrupting controlled manufacturing or inspection activities. Identify any access accommodation or document-access request early, because approval may depend on confidentiality, safety and project requirements.

Customer observation does not authorize visitors to operate, adjust, open or test equipment. Installation, servicing, testing and energization require qualified personnel working under approved procedures; witness attendance does not replace those controls. The agenda should identify the manufacturer’s designated host and explain how questions, interruptions or safety concerns will be handled. If a planned activity cannot be conducted safely under the approved arrangement, it should be paused and escalated through the agreed project contacts.

Record observations and close out findings

Agree in advance what the witness record will contain: equipment identification, procedure and revision, date, attendees, activities observed, recorded results, exceptions and referenced documents. Distinguish an observed result from a customer’s acceptance of the equipment or from a final contractual disposition. Where a witness cannot attend a point, record the agreed alternative, such as proceeding under the project’s stated notice rules or rescheduling if the parties approve.

For a deviation or disputed result, document the specific requirement, observed condition, supporting evidence and responsible party for follow-up. Define who evaluates the issue, whether additional inspection or retesting is required, and how closure will be recorded. Reports and test records should be limited to the agreed deliverables; availability, format, approval process and delivery timing must be confirmed for the project. This creates a traceable closeout without implying that a particular test or report is automatically supplied.

LET'S BUILD SOMETHING

Start with
the details.

Tell us what you’re working on. The more you can share about your project, the better we can begin the conversation.

PROJECT INQUIRY

Request a quote

This form opens your default email application. Your inquiry is sent only when you send the email. You can also email us directly or call our team.

* Required fields

Request a quote